Apache Trail – Weekly Report 03/20/23 to 03/24/23
Apache Trail – Weekly Report 03/20/23 to 03/24/23 This project involves roadway reconditioning, culvert cleaning, minorand major drainage improvements, parking lot improvements, chip seal surfacing andpavement on the steep sections. Work in progress SWP continued with culvert installations at STA