Apache Trail – Progress Report 02/13/23 to 02/17/23

Apache Trail - Progress Report 02/13/23 to 02/17/23

This project involves roadway reconditioning, culvert cleaning, minor and major drainage improvements, parking lot improvements, chip seal surfacing, and pavement on the steep sections. 

Work in progress

  • SWP removed corrugated metal pipes on site
  • SWP resumed laying back the slope (roadway excavation) at STA 1528+00 – 1532+00
  • SWP led a preparatory meeting for the upcoming culvert pipe installation.
  • SWP is screening material excavated on site
  • Concrete subcontractor produced color samples for colored concrete submittal

Upcoming work activities

02/13/23 to 02/17/23

  • SWP expects to finish roadway excavations at 1528+00 – 1532+00 & begin excavation work at 1477+10 – 1478+50
  • SWP anticipates starting the installation of pipe culverts

 

Apache Lake Renovation

SWP excavator hammering off rocks from slope (STA 1530+00)

Apache Lake Renovation

SWP using a loader & mobile screener to sieve material from roadway excavation (STA 1370+00)

Apache Lake Renovation

Material supplier, Payson Concrete & Material, & subcontractor, ACS Concrete, pouring concrete samples (Payson Concrete & Material, Tonto Basin, AZ)

Apache Lake Renovation

SWP staging pipes for upcoming culvert work (STA 1365+00)

Apache Lake Renovation

Local fauna parading on work site, STA 1645+00