Apache Trail - Progress Report 02/13/23 to 02/17/23
This project involves roadway reconditioning, culvert cleaning, minor and major drainage improvements, parking lot improvements, chip seal surfacing, and pavement on the steep sections.
Work in progress
- SWP removed corrugated metal pipes on site
- SWP resumed laying back the slope (roadway excavation) at STA 1528+00 – 1532+00
- SWP led a preparatory meeting for the upcoming culvert pipe installation.
- SWP is screening material excavated on site
- Concrete subcontractor produced color samples for colored concrete submittal
Upcoming work activities
02/13/23 to 02/17/23
- SWP expects to finish roadway excavations at 1528+00 – 1532+00 & begin excavation work at 1477+10 – 1478+50
- SWP anticipates starting the installation of pipe culverts

SWP excavator hammering off rocks from slope (STA 1530+00)

SWP using a loader & mobile screener to sieve material from roadway excavation (STA 1370+00)

Material supplier, Payson Concrete & Material, & subcontractor, ACS Concrete, pouring concrete samples (Payson Concrete & Material, Tonto Basin, AZ)

SWP staging pipes for upcoming culvert work (STA 1365+00)

Local fauna parading on work site, STA 1645+00