This project involves roadway reconditioning, culvert cleaning, minor and major drainage improvements, parking lot improvements, chip seal surfacing, and the pavement on the steep sections.
WORK IN PROGRESS
• SWP directed a startup meeting for culvert pipe installation
• SWP installed culvert pipes at STA 1324+62 & 1328+72
• SWP cleared & grubbed culvert areas from 1252+75 to 1472+32
• SWP continued sorting roadway excavation material
• SWP resumed road maintenance near culvert work areas
UPCOMING WORK ACTIVITIES
03/06/23 to 03/10/23
• SWP will continue removing & replacing culvert pipes
• SWP expects to commence placing riprap at culvert outlets
• An archaeologist will be present to monitor work areas during culvert construction
• Equipment mobilization is anticipated to resume






